My Oracle Support Banner

OTM Not Planning Shipment With The Cheapest Cost Equipment Group When Available (Doc ID 2187523.1)

Last updated on JULY 20, 2024

Applies to:

Oracle Transportation Operational Planning - Version 6.0 and later
Oracle Transportation Management - Version 6.0 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
An order is planned onto a shipment using the bulk plan action. There are several valid equipment assignments (within the same equipment group profile) and service providers that can service the shipment. When planning the shipment, OTM is not selecting the cheapest cost equipment to be used.

If the order is constrained to the desired equipment group (cheapest option), the shipment is planned with the desired result.


EXPECTED BEHAVIOR
-----------------------
It is expected that OTM select the cheapest cost equipment for the shipment without having to constrain the order.

STEPS
-----------------------
The issue can be reproduced with the following steps:

1. Bulk plan an order within a lane that contains multiple options for equipment assignments with varying rates (with all equipment options within the same equipment group profile).
2. The resulting shipment will be planned with an equipment that is not the cheapest option.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.