R12: PSI Form: Column 'ITD - Rev Bgt' Shows Incorrect Amount For 1 Project
(Doc ID 2189696.1)
Last updated on NOVEMBER 15, 2022
Applies to:
Oracle Project Planning and Control - Version 12.1.3 and laterInformation in this document applies to any platform.
Symptoms
On : 12.1.3 version, Status Reports
ACTUAL BEHAVIOR
---------------
For Project Number <project number>:
PSI form shows column 'ITD - Rev Bgt' = 1033066.
However, in the Budget form, both Raw Cost and Burdended Cost shows 0.00 for the same.
-The issue is with the PSI form. The column 'ITD - Rev Bgt' should show 0.00 as well.
This only happens to 1 project
-Customer ran the following process but issue still exists:
PRC: Update Project Summary Amount
PRC: Refresh Project Summary Amount
EXPECTED BEHAVIOR
-----------------------
The column 'ITD - Rev Bgt' should show 0.00.
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. PSI form:
Current Period = MAY-2016
Project = <project number>
ITD - Rev Bgt = 1033066
2. In Budgets form:
Project Number = <project number>
Budget Type = Approved Cost Budget
Status = submitted
Current:
Quantity = 0.00
Raw cost = 0.00
Burdended Cost = 0.00
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |