Receiving Inspection amount is not same as Inventory Valuation amount when material overhead is defined. Items are received with PO (purchase order) unit price:184.01 x quantity:640 (=total amount:117766.4) , but Receiving Inspection amount is calculated = 117767. Why there is one amount mismatch here?

Reproducing Steps:

  1. Currency precision is set to 0.
  2. Material overhead is defined as below;
    • Overhead1: 0.025 (total amount basis, resource_id =4561)
    • Overhead2: 16.96 (item basis, resource_id =4562)
    • Overhead3: 0 (item basis, resource_id =4563)
  3. Receive PO with PO unit price:184.01, quantity:640.
  4. Deliver them to Inventory.
  5. Material Transaction Distribution records are created as below; 
Accounting_Line_Type_id Cost_Element_ID Primary_Quantity Base_Transaction_Value Rate_or_Amount Resource_Id
1- Inventory Valuation 1 - Material 640 117766 184.01  
1- Inventory Valuation 2 - Material Overhead 640 13799 21.56025  
5- Receiving Inspection   -640 -117767 184.01  
3- Material Overhead Absorption 2 - Material Overhead -640 -2944 4.60025 4561
3-Material Overhead Absorption 2 - Material Overhead -640 -10854 16.96 4562
3-Material Overhead Absorption 2 - Material Overhead -640 0 0 4563

 

 

 

 

 

 

 

Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Goal
Solution


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.