Purpose

The purpose of this document is to aid Users in setting up planning attributes of Items in Oracle Inventory.

Scope

The scope of this document is to offer information on setting up Inventory Items for use in Material Requirements Planning (MRP) and Master Production Schedule (MPS).

Details

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Purpose
Scope
Details
 Define Items MPS/MRP Planning Attribute Group
 Planning Method
 ORACLE MASTER SCHEDULING/MRP AND SUPPLY CHAIN PLANNING ONLY
 Forecast Control
 ORACLE MASTER SCHEDULING/MRP AND SUPPLY CHAIN PLANNING ONLY
 Exception Set
 Pegging
 Enter the pegging option.
 Planned Inventory Point
 Create Supply
 ORACLE ADVANCE PLANNING AND SCHEDULING ONLY
 Round Order Quantities
 ORACLE MASTER SCHEDULING/MRP AND SUPPLY CHAIN PLANNING ONLY
 Shrinkage Rate
 ORACLE MASTER SCHEDULING/MRP AND SUPPLY CHAIN PLANNING ONLY
 Acceptable Early Days
 ORACLE MASTER SCHEDULING/MRP AND SUPPLY CHAIN PLANNING ONLY
 Repetitive Planning
 ORACLE MASTER SCHEDULING/MRP AND SUPPLY CHAIN PLANNING ONLY
 Overrun Percentage
 ORACLE MASTER SCHEDULING/MRP AND SUPPLY CHAIN PLANNING ONLY
 Acceptable Rate Decrease
 ORACLE MASTER SCHEDULING/MRP AND SUPPLY CHAIN PLANNING ONLY
 Acceptable Rate Increase
 ORACLE MASTER SCHEDULING/MRP AND SUPPLY CHAIN PLANNING ONLY
 Calculate ATP
 ORACLE MASTER SCHEDULING/MRP AND SUPPLY CHAIN PLANNING ONLY
 Reduce MPS
 ORACLE MASTER SCHEDULING/MRP AND SUPPLY CHAIN PLANNING ONLY
 Planning Time Fence
 ORACLE MASTER SCHEDULING/MRP AND SUPPLY CHAIN PLANNING ONLY
 Planning Time Fence Days
 ORACLE MASTER SCHEDULING/MRP AND SUPPLY CHAIN PLANNING ONLY
 Demand Time Fence
 ORACLE MASTER SCHEDULING/MRP AND SUPPLY CHAIN PLANNING ONLY
 Demand Time Fence Days
 ORACLE MASTER SCHEDULING/MRP AND SUPPLY CHAIN PLANNING ONLY
 Release Time Fence
 ORACLE MASTER SCHEDULING/MRP AND SUPPLY CHAIN PLANNING ONLY
 Release Time Fence Days
 ORACLE MASTER SCHEDULING/MRP AND SUPPLY CHAIN PLANNING ONLY
 Substitution Window