Unable to Allocate Hard Pegged Expense Item in Project Locator

(Doc ID 2315403.1)

Last updated on OCTOBER 09, 2017

Applies to:

Oracle Inventory Management - Version 12.2.4 and later
Information in this document applies to any platform.

Symptoms

On : 12.2.4 version, Pick Release

If checkbox of "Allow Cross Project Pick Wave Allocation" is unchecked, when attempting to allocate pick wave move order for hard pegged expense item even if onhand project/task is
same as project/task on the sales order,  following error occurs.


ERROR
-----------------------
"The material sourcing process failed to create picking suggestions for line 1 of move order number XXXX.".

In addition, INV debug was showing the error as below:


STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Responsibility: Inventory Super User
2. Navigation: Move Orders -> Transact Move Orders
3. Query the move order.
4. Attempt to allocate, get the error.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms