Symptoms

ACTUAL BEHAVIOR
A PPR Template is configured with a Payment Date of 1 extra day. When a PPR is created via scheduled recurring PPR using the template, it is actually 2 days extra.

EXPECTED BEHAVIOR
Payment date should be calculated according to PPR template settings.

STEPS
The issue can be reproduced at will with the following steps:
1. Configure PPR template with 1 extra day for payment
2. Submit PPR with template on 1 Nov 2017 by scheduled PPR
3. Observe payment date on PPR is set to 3 Nov 2017

BUSINESS IMPACT
The issue has the following business impact:
Due to this issue, payments must be cancelled and paid manually to ensure the appropriate date is used.

Cause

Sign In with your My Oracle Support account