Symptoms
When the resource approval is initiated with a Single record then the following behavior is happening:
ACTUAL BEHAVIOR
------------------------
Approval Status: Working
EXPECTED BEHAVIOR
-----------------------
Approval Status: Submitted
STEPS
----------
The issue can be reproduced at will with the following steps:
1. Project Super User responsibility > search for Project Number
2. On the Resources tab
Select the respective Team Role having a valid start date and end date and enter the effort hours.
The Schedule Status is Provisional.
The Approval Status is Working.
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |
References |