PAPA_NO_BUDGET_YEAR_DEFINED Error Occurs While Baselining Project Budget
(Doc ID 2353409.1)
Last updated on NOVEMBER 15, 2022
Applies to:
Oracle Project Planning and Control - Version 12.2.2 and laterInformation in this document applies to any platform.
Symptoms
On : 12.2.7 version, Budgeting & Forecasting
Please budget account generator is generating the account but its not getting baselined
ERROR
-----------------------
PAPA_NO_BUDGET_YEAR_DEFINED
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. create a new budget
2. baseline the budget
BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Project Budget cannot be baselined.