PAAPIMP:PRC: Interface Supplier Costs Errors: The Item Date Is Not Within The Project Active Dates
(Doc ID 2391251.1)
Last updated on DECEMBER 10, 2024
Applies to:
Oracle Project Costing - Version 12.1.3 and laterInformation in this document applies to any platform.
Symptoms
When running PRC: Interface Supplier Costs, the following exception is encountered:
The item date is not within the project active dates
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |