R12: PAAPIMP:PRC: Interface Supplier Costs Errors: The Item Date Is Not Within The Project Active Dates
(Doc ID 2391251.1)
Last updated on JUNE 07, 2021
Applies to:
Oracle Project Costing - Version 12.1.3 and laterInformation in this document applies to any platform.
Symptoms
When running PRC: Interface Supplier Costs, the following exception is encountered:
The item date is not within the project active dates
Cause