R12: Funds Check Discrepancy Between Summary And Detail Actuals
(Doc ID 2411543.1)
Last updated on JULY 31, 2023
Applies to:
Oracle Project Costing - Version 12.1.3 and laterInformation in this document applies to any platform.
Symptoms
There are discrepancies with Summary and Detail Actual amounts for some projects:
Example:
At Budget options:
Project Number = 25006
Budget Type Approved Cost Budget
Click History button
Tools - View Funds Check Results
Click Details button for Actuals
Comparing the Totals figures, there is a variance:
6,396,537.23 Total Actuals Details window
6,161,560.78 Total Summary tab
234,976.45 Variance
Workaround:
-Open the GL period in General Ledger
-Submit the Baseline for the Project in order to refresh the Actuals amount at the Summary tab.
This refreshes the amounts as a workaround. But the Actual amount was already there at Project Status Inquiry.
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |
References |