Project Workplan Tasks Copied In Reverse Order

(Doc ID 2420243.1)

Last updated on JULY 06, 2018

Applies to:

Oracle Project Planning and Control - Version 12.2.5 and later
Information in this document applies to any platform.

Symptoms

On : 12.2.5 version, Workplan

Project workplan tasks copied in reverse order

When copying workplan WBS more than one task from one position to another position in the structure they are copied in reverse order as specified in wbs.


Steps:
1. Projects: Delivery->Search Project (specify Project Number) Go
2. Click on project name
3. Click on Workplan tab
4. Select multiple tasks in sequence
5. Click Copy button
6. Select target task
7. Click Paste Select "As subtask"
8. Enter the prefix
9. Click Apply
10. When the tasks are displayed, they are in reversed order than the original

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms