Symptoms
When user attempt to add a new task in the child program project the following error is received:
"You have charged a supplier invoice to this task with a finish date that is after the task finish date. Please revise the task finish date so that it is the same or later than the supplier invoice finish date: 'DD-MON-YYYY'."
Steps to reproduce:
1. Enter Project Number
2. Navigate to Workplan Tab: All Tasks > Go
3. Select the Project Name
4. Actions > Update Tasks > Go
5. Choose ‘Select’ on the last Task Number.
6. Create Task
7. Complete Task Number, Task Name, Scheduled Start/Finish
8. Apply
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |
References |