R12 Create An Extra Task Under Workplan and receive "You have charged a supplier invoice to this task with a finish date that is after the task finish date."
(Doc ID 2467303.1)
Last updated on JANUARY 11, 2021
Applies to:
Oracle Project Planning and Control - Version 12.1.3 and laterInformation in this document applies to any platform.
Symptoms
On : 12.1.3 version, Costing Setup
User is trying to create an extra task under Workplan in Oracle Projects.
STEPS
----------------------
- Enter Project Number
- Go
- Select the Project
- Workplan Tab
- All Tasks > Go
- select the Project Name
- Actions > Update Tasks > Go
- Tick ‘Select’ on the last Task Number.
- Create Task
- Complete Task Number, Task Name, Scheduled Start/Finish
- Apply
When publish the workplan got the following error:
Ran the following SQL query script which did not pull through the particular Project/Invoice -
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |