Exception In PRC: Summarize Unbilled Receivables/Unearned Revenue Balances Process
(Doc ID 2690968.1)
Last updated on OCTOBER 10, 2022
Applies to:
Oracle Project Billing - Version 12.1.3 and laterInformation in this document applies to any platform.
Symptoms
On : 12.1.3 version, Revenue
When attempting to run PRC: Summarize Unbilled Receivables/Unearned Revenue Balances Process, the following error occurs.
ERROR
-----------------------
From the debug log, getting following error "Exception-2=ORA-20120: Currency Conversion Rate Not Defined In The System"
Steps to Reproduce the Issue
---------------------------------
The issue can be reproduced at will with the following steps:
1. Go to Projects Responsibility
2. Navigate to View-> Request-> Submit-> PRC: Summarize Unbilled Receivables/Unearned Revenue Balances Process
3. Verify if project invoices and revenues are successfully balanced
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |