Project Budget Baseline Is Rejected With A Funds Check Result Code Of F111
(Doc ID 2810996.1)
Last updated on JULY 19, 2024
Applies to:
Oracle Project Costing - Version 12.2.7 and laterInformation in this document applies to any platform.
Symptoms
When baselining a project budget it fails and results in a Rejected status.
When the baseline is performed there are sufficient funds available to allow the budget to baseline.
The workflow notification shows the error code PAPA_BC_BASELINE_FCHK_FAILED
The Funds Check Result Code = F111 - The transaction failed budgetary control at the top task level will be shown in Transaction Funds Check Results
These steps can be reproduced with the following steps
- Log into a Projects responsibility
- Navigate to Budgets
- Enter project number
- Enter budget type
- Click Find
- Click Submit
- After workflow is approved, completes process or if approval is not required, the budget status will be Rejected.
Changes
Update to a budget.
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |
References |