PARGDR PRC: Generate Draft Revenue Error No Funding/Hard Limit (Doc ID 2869754.1)

Last updated on JANUARY 29, 2024

Applies to:

Oracle Project Billing - Version 12.1.1 and later
Information in this document applies to any platform.

Symptoms

PARGDR PRC: Generate Draft Revenue concurrent process  completed with below error 

Error

No Funding/Hard Limit

Steps to reproduce the issue

1.Go into the Project Responsibility 

2 Navigate to View-> Request

3 Run the concurrent process PRC: Generate Draft Revenue

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
 Possible Cause 1 : Hard Limit is Enabled for the agreement
 Possible Cause 2 : Billing Funds Check by Funding Classification is enabled on the Agreement/Funding used for the problem Project 
 Possible Cause 3 : Insufficient Funding
 Possible Cause 4 : A project was funded at the project level and revenue was generated. The funding was then zeroed out, and re-entered at the task level.
 Possible Cause 5 : Billing Fund Check by Funding Classification was enabled
 Possible Cause 6 : Task level funding not exists 
 Possible Cause 7 : Funding is done using Project Contracts (OKE)
 Possible Cause 8 : Customer or Bill To or Ship To  not active 
 Possible Cause 8 : When Funds Check by funding classification is enabled then PRC: Generate Draft Revenue process not generating the revenue for an event
 Possible Cause 9 : If the event Completion Date has some timestamp Value and the Accrue Through Date entered is same as event Completion Date.
 Possible Cause 10 : When a project has two customers with bill split 100 and 0, the revenue is generated double the expected amount.