WIP Mass Load Program Takes Long Time When Multiple Wrappers Programs Run in Parallel
(Doc ID 2905307.1)
Last updated on NOVEMBER 03, 2022
Applies to:
Oracle Work in Process - Version 12.2.7 and laterInformation in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
The WIP Mass load program is taking long time. It should finish in 30 minutes but it takes 2 hours especially when multiple wrappers programs are run in parallel.
EXPECTED BEHAVIOR
WIP Mass load program to finish in 30 minutes.
STEPS
The issue can be reproduced at will with the following steps:
1. Responsibility: Work In Process.
2. Run WIP Mass Load program while multiple wrappers are running.
3. Observe the program takes about 2 hours to complete.
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |