PAXTRAPE: Project Burdened Cost Amounts not Visible for Certain Expenditure Items in the Expenditure Inquiry for a Single Project.
(Doc ID 2913162.1)
Last updated on JANUARY 31, 2023
Applies to:
Oracle Project Costing - Version 12.2.9 and laterInformation in this document applies to any platform.
Symptoms
Expenditure items show no Project Functional Burdened Cost amount in the Expenditure Inquiry. This is only an issue with this project
Steps to Reproduce:
1. Project Costing Super User responsibility
2. Expenditure | Expenditure Inquiry | Project
3. Query the particular adjusted items and note that no cost is shown
Changes
Expenditure Items were adjusted in Projects once imported
Cause