My Oracle Support Banner

PAXPREPR: After 12.2.10 Upgrade: Project Cost Burden Schedules Screen Is Grayed Out and Missing List Of Values (LOV) (Doc ID 2929924.1)

Last updated on FEBRUARY 28, 2023

Applies to:

Oracle Project Foundation - Version 12.2.10 and later
Information in this document applies to any platform.

Symptoms

After upgrading from 11.5 to 12.2.10, in the Projects form under the Burden Multipliers >> Cost Burden Schedules option,
the "Burden Schedule" field has a defaulted value but it is grayed out and there is no list of values (LOV) to select from.

This happens for existing and newly created projects.


Reproducible Steps
=============

Using a Projects responsibility:

1. Navigate to Projects

2. Open an existing project

3. Go to Options >> Burden Multipliers >> Costing Burden Schedules
-The "Burden Schedule" field is defaulted in with value.
-This field is grayed out and there is no LOV to select from.

Changes

 Upgraded to R12.2.10

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution