When Creating Standard Job For The Assembly Item, The Component Required Quantity On Job Material Requirements Form Displayed Is Greater Than The Component Quantity Defined On The Bills Of Materials.
(Doc ID 2973746.1)
Last updated on SEPTEMBER 12, 2023
Applies to:
Oracle Work in Process - Version 12.2.11 and laterInformation in this document applies to any platform.
Symptoms
When creating standard job for the assembly item, the component required quantity on job material requirements form displayed is greater than the component quantity defined on the Bills of Materials.
Expect that when creating standard job for the assembly item, the component required quantity on job material requirements form displayed must be equal to the component quantity defined on the Bills of Materials.
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1.Login to Work in Process responsibility
2.Discrete > Discrete Jobs > Create Work order > Components
3.Observe the component required quantity on job material requirements form displayed is greater than the component quantity defined on the Bills of Materials.
4.Login to Bill of Materials responsibility
5.Bills > Indented Bills > Enter the Assembly Item > Click Find > Indented Bills of Materials > Quantities > View Component Quantities
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |