Symptoms

ACTUAL BEHAVIOR
----------------
When releasing the Planned Order from ASCP, po_requisitions_interface_all table has correct quantity - 208 (fixed order quantity qty).

Later on, the 208 qty appear on each PO Line from a single PO .

 

EXPECTED BEHAVIOR
------------------
Each new PO/ Planned order released from ASCP plan , to have have on PO Line the quantity of 208.

example:
1PO Line1 - 208 qty
2PO Line1 - 208 qty
3PO Line1 - 208 qty
...................
208PO Line 1 - 208 qty

The problem is, 1 PO is created with 208 PO Lines each having 208 qty.

 

STEPS TO REPRODUCE
--------------------
1. data inserted in po_requisitions_interface_all table has correct quantity - 208 (fixed order qty)

2. profile MRP : Requisition Load Group Option to : Item

3. Several plan lines(208 lines) are released.

4. Requisition is created with 208 lines
and
Purchase order is also created with 208 lines.

 

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.