My Oracle Support Banner

How To Approve a Purchasing Document Submitted in the Previous (now Closed) GL Period (Doc ID 373028.1)

Last updated on DECEMBER 11, 2019

Applies to:

Oracle iProcurement - Version 11.5.8 to 12.1 [Release 11.5 to 12.1]
Oracle Purchasing - Version 11.5.8 to 12.1 [Release 11.5 to 12.1]
Information in this document applies to any platform.
iProcurement - Version: 11.5.8 to 12.1
FORM:POXRQERQ.FMB - Enter Requisitions GUI
FORM:POXPOEPO.FMB - Enter Purchase Orders GUI
ConcurrentProgram:REQIMPORT - Requisition Import
ConcurrentProgram:POXPOPDOI - Import Standard Purchase Orders


Goal

What steps can be taken to either avoid, or resolve these cases?

CASE I
1. Under an Encumbrance Enabled environment, a Requisition created in May with a default
    GL Date of May 2006, is submitted for approval.

2. The Requisition is Approved with the final Approver in the hierarchy approving in June of 2006.
    The GL Period for May 2006 is closed.

3. The Requisition is Approved, and then Rejected immediately after approval.

4. To resubmit this Requisition the user changes the GL date to June's date and resubmits the
    same for approval.

5. However, since the Requisition has already been Approved, this can create confusion
    for the Approvers.

CASE II
1. Under an Encumbrance Enabled environment, Requisitions are imported in June with a GL Date 
    set to May 2006.

2. The Requisition is submitted for approval or initiated for approval through the
    Requisition Import process.

3. The GL Period for May 2006 is closed.

Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Goal
Solution
References

My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.