My Oracle Support Banner

Can't Add Planning Resource For Material items - Item Category LOV Blank (Doc ID 553618.1)

Last updated on JANUARY 09, 2024

Applies to:

Oracle Project Planning and Control - Version 11.5.10.2 and later
Information in this document applies to any platform.

Symptoms

When trying to create a new planning resource for a Planning Resource List,
unable to do so with the following parameters:

Resource Class: Material Items
Resource Format: Item Category
Name: <anything>
Item Category: M-SM

When trying to enter the final data, Item Category, there is no LOV and cannot continue.

1. Select Projects:Setup>Planning Resource Lists
2. Create a new Planning Resource List
2a. Select Enabled for Workplan
2b. Select Centrally Controlled
3. Under the Planning Resource Formats tab, select Material Items
4. Click Add Resource Formats
5. Set Resource Class to Material Items and click (Go)
6. Select Item Category and click (Apply)
7. Go to the Planning Resources tab
8. Set Resource Class to Material Items
9. Set Resource Format to 'Item Category
10. Click (Add Single Planning Resource)
11. On the next screen, set the following...
Resource Class: Material Items
Resource Format: Item Category
Name: test
Item Category: []
Will not be able to continue because there is no LOV for Item Category

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution

My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.