Outside Processing (OSP): Job Gets Completed Without Backflush Components Issue (Doc ID 554132.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Work in Process - Version 11.5.10.2 to 11.5.10.2 [Release 11.5]
Information in this document applies to any platform.

Goal

Scenario:
When Outside Processing (OSP) assemblies are received from the supplier, the system will perform move and completion transaction (as charge type is PO Move and OSP operation is the last operation), hence the job is completed. However, due to insufficient onhand quantity for backflush items, there are records lying in pending move transaction at Backflush Phase with appropriate error message.

Without issuing the backflush components to the job, why is the job being completed and assembly item getting inventorised without issuing the child components?



Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms