Overcoming Currency Error On Commitment (Doc ID 729507.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Project Costing - Version 11.5.10.0 to 11.5.10.0 [Release 11.5.10]
Information in this document applies to any platform.

Goal

An error comes up when running PRC: Update Project Summary Amounts which says
'Commitment currency conversion errors were encountered'.

Project i is complaining it has a Project currency of USD. PO is entered is EUR. Both have
different RATE TYPES. Project Functional currency is GBP.
When entering a rate to the Project Currency Type for the Expenditure Item Date of the PO
for USD to EUR (and vice versa). Where is the missing rate held? Is the date correct?

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms