PTO Carry Over Not Working For Anniversary Date That Is Mid-Month (Doc ID 761386.1)

Last updated on MARCH 03, 2017

Applies to:

Oracle Human Resources - Version 12.0.6 and later
Information in this document applies to any platform.
***Checked for relevance on 31-Jan-2011***


Symptoms

-- Problem Statement:
Run the carryover process on anniversary date of the employee whose hire date is not the 1st of a
month, the carryover does not carry the the net entitlement due in next cycle. For employees whose
hire dates are the 1st of a month, the carryover works fine.

EXPECTED BEHAVIOR
Expect the PTO Carryover work fine for employees whose hire dates is not 1st of a month

-- Steps To Reproduce:
The issue can be reproduced at will with the following steps:
1. Existing Person is enrolled onto Annual Plan with an effective date from 01-Mar-2009. Person's hire date is 15-Mar-2006
2. Add an extra balance element entry for say 10 days (this is extra balance available)
3. Run the PTO Carry Over process on 15-Mar-2010.
4. No Carryover Balance

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms