Goal

When trying to update the status of a standard discrete job from "Complete" status to "Complete
- No Charges" status through WIP Mass Load program. In the output of WIP Mass Load request, it is mentioned "You can only update jobs to Unreleased, Released, Complete, On Hold, or "Cancelled".

But same status change (from Complete to Complete - No Charges status) is possible from Discrete Job form.