My Oracle Support Banner

Pre-Encumbrance Stuck After Closing Finalized PO and Closing Requisition (Doc ID 2184370.1)

Last updated on OCTOBER 01, 2024

Applies to:

PeopleSoft Enterprise SCM Purchasing - Version 9.1 to 9.2 [Release 9]
Information in this document applies to any platform.

Symptoms

Pre-encumbrance stuck after closing finalized PO and closing requisition.

1) Create a requisition. Approve and budget check.
2) Copy req into a new PO. DO NOT approve or budget check.
3) Finalize the PO distrib. Save PO but DO NOT approve or budget check.
4) Cancel the PO (do not undo finalize).
5) Close the PO.
6) Close the requisition.
7) Pre-encumbrance is still populated and cannot be liquidated from the budget.

NOTE:  This is similar to Doc ID 2093306.1, but in this case the PO is closed (step 5 above) after it is canceled.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.