Nightly SJT Refresh Process page (SCRTY_SJTDLY) it is Taking over Seven (7) Hours to Complete (Doc ID 2260554.1)

Last updated on APRIL 28, 2017

Applies to:

PeopleSoft Enterprise HCM Human Resources - Version 9.2 to 9.2 [Release 9]
Information in this document applies to any platform.

Symptoms

When Running the Nightly SJT Refresh Process page (SCRTY_SJTDLY) it is Taking over seven (7) Hours to Complete.

EXPECTED BEHAVIOR
-----------------------
The SJT Nightly Refresh Process should Complete more Rapidly so as to not impact Human Resource Hiring.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Navigate: Setup HCM > Security > Core Row Level Security > Nightly SJT Refresh Process > Nightly SJT Refresh Process
2. Complete Run Control Settings for Daily
3. Submit Run Control for Processing
4. Process is Taking Approximately 7 Hours to Complete 40,000 Job Row Changes
5. Process Completed Update for 1750 users per hour.


Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms