Symptoms

On : 9.2 version, Campus Community Other
 
Our  holiday schedule was set up with
November 12 2022 - Armistice day
November 21 2022 - Thanksgiving
After setting up the holiday schedule we created attendance rosters and realized those were not the correct holiday dates.  

We corrected our holiday calendar to reflect the correct dates.
November 11 2022 - Armistice day
November 24 2022 - Thanksgiving
and re-generated attendance rosters, but the original dates November 12 and November 21 are still designated as holidays on the attendance roster.

 
The issue can be reproduced at will with the following steps:
1. Go to Schedule of Classes & Enter Meetings Pattern.
2. Go to Set Up Common Objects - Foundation Tables - Organization - Holiday Schedule. Verify Holiday Schedule
3. Generate Attendance Roster
4. Verify Attendance Template
5. Modify Holiday Schedule
6. Re-Generate Attendance Roster
7. Verify Attendance Template, Notice that there is no change in the attendance templates.


Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.