EPC: Incremental/Full Sync (PROJECT_STATUS_SYNC/PROJECT_STATUS_FULLSYNC) For Project Status Is Sending Summary Project Information From FSCM to HCM (Doc ID 2548664.1)

Last updated on FEBRUARY 01, 2023

Applies to:

PeopleSoft Enterprise FIN Project Costing - Version 9.2 to 9.2 [Release 9]
Information in this document applies to any platform.

Symptoms

On : Project Costing 9.2

ACTUAL BEHAVIOR
---------------
The PROJECT_STATUS_SYNC/PROJECT_STATUS_FULLSYNC integration sends summary/program projects to HCM.

EXPECTED BEHAVIOR
-----------------------
The PROJECT_STATUS_SYNC/PROJECT_STATUS_FULLSYNC should not sent summary project status to HCM

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Configure PROJECT_STATUS_SYNC/PROJECT_STATUS_FULLSYNC service operations between FSCM and HCM nodes
2. Create a Project as a summary project
3. Notice that the Project status is being sent to HCM. It should not
4. The PROJECTSTATUS_FULL_SYNC is also sending the summary project status information to HR. It should not

Following bug addresses the Project_FULLSYNC issue
<Bug 28606099> - PROJECT_FULLSYNC IS INCORRECTLY SENDING SUMMARY PROJECTS UNLIKE PROJECT_SYNC

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.