EPC 9.2: Project Copy Performance Issue (Doc ID 2865558.1)

Last updated on SEPTEMBER 22, 2023

Applies to:

PeopleSoft Enterprise FIN Project Costing - Version 9.2 to 9.2 [Release 9]
Information in this document applies to any platform.

Symptoms

When copying a project with more than 300 resources, the system produces a time-out after 5 minutes and the user is kicked out of the system.

REPLICATION STEPS:

1. Navigate to Project Costing / Project Definitions / Define Project General Info and create a project that has 9 activities.
The project has 333 resources, who have all been added to the 9 activities.
2. Scroll to the bottom of the page and press Copy Project.
Copy the project and all activities, including the resources.



Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!