EPC 9.2 : When Cost Collection Purchasing Adj Is Run With Partial Commitment Transaction Adjustment, PC_POADJUST Process ABENDED at Step PC_POADJUST.PR_INS.COPY_DE2 (Action SQL) -- RC = 805
(Doc ID 2929506.1)
Last updated on SEPTEMBER 20, 2024
Applies to:
PeopleSoft Enterprise FIN Project Costing - Version 9.2 to 9.2 [Release 9]Information in this document applies to any platform.
Symptoms
When cost collection purchasing adj is run with partial commitment transaction adjustment, the PC_POADJUST process abends with the following error message.
Replication Steps:
- Installation Options for Project Costing shows the PO Reversal as "ACT Amount".
- Create a new project and 2 activities.
- Create a PO - $850. Assign the project/activity.
- Create a voucher - $320. Copy from PO and change the amount to $320.
- Run PC_PO_TO_PC, PC_AP_TO_PC and PC_POADJUST. COM/ACT/CRV rows are created. (Navigation: Project Costing > Cost Collection > Cost Collection Purchasing, Cost Collection Payables, Cost Collection Purchasing Adj processes respectively)
- Do transaction adjustments to transfer $320.13 COM to the new activity.
- Do transaction adjustments to transfer $320.13 ACT to the new activity with chart field change.
- Close the PO.
- Run the PC_POADJUST and the process goes to success and a CCA row gets generated. (Navigation: Project Costing > Cost Collection > Cost Collection Purchasing Adj processes)
- Run the PC_POADJUST again and the process abends with the above error in the message log and traces. (Navigation: Project Costing > Cost Collection > Cost Collection Purchasing Adj processes)
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |