Requisition Mass Change Is Creating Second Distribution Line With Values Already Copied From the First Distribution Line
(Doc ID 2986013.1)
Last updated on NOVEMBER 08, 2023
Applies to:
PeopleSoft Enterprise SCM eProcurement - Version 9.2 to 9.2 [Release 9]Information in this document applies to any platform.
Symptoms
When creating a requisition with several lines, then using the mass change option to add additional distributions and leaving the second distribution line with blank information fields , Mass change will default the first distribution line to the second line.
The issue can be reproduced at will with the following steps:
- Navigate to eProcurement tile > Create Requisition and create a new requisition
- Press on requisition defaults and enter some chart field information like Fund, Dept, Program , Class and so on
- Add several special request items.
- Check out then select one or two lines and from the action menu choose mass change.
- Add additional distribution line on the mass change page and leave some fields like project and project BU blank on the second distribution line.
- Change the option : Change Apply Distribution Changes fields = Replace Distribution Lines
- Now review the changes done on the requisition distribution.
- Notice that the second distribution line has all the values from the first distribution line and fields are not blank as they should be.
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |