EPC 9.2: When Finalizing the Budgets Loaded via PS_INTFC_PROJ_RES Using the Program PC_INTFEDIT, the Budget Transactions Result in the Exceptions - "Exceeds Parent Budget". The Error Code Observed in Trace is E50.
(Doc ID 3000370.1)
Last updated on JANUARY 29, 2024
Applies to:
PeopleSoft Enterprise FIN Project Costing - Version 9.2 to 9.2 [Release 9]Information in this document applies to any platform.
Symptoms
When finalizing the budgets loaded via INTFC_PROJ_RES using the program PC_INTFEDIT, the budget transactions result in the below exceptions.
Error:
In the trace, found that the rows are coded with an E50 error code which means "Exceeds Parent Budget."
Replication Steps:
- Using SQL or another method, load data into INTFC_PROJ_RES from a third-party system. These are budget rows.
- Run the PC_INTFEDIT process for the specific interface ID. (Project Costing > Third Party Integration > Third Party Load Transactions)
- Budgets are loaded into the Budget Plan and the Budget Detail tables. Navigate to Project Costing > Budgeting > Budget Plan. Open the budget plan and click on the Finalize button of the budget plan to finalize the budget.
- Notice that the budgets are not processed to KK and are errored with budget exceptions. The exception says the child's budget exceeds the parent's budget.
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |