Approve Change Request Not Showing Second Changes When Run Multiple Change Request
(Doc ID 3028884.1)
Last updated on JUNE 19, 2024
Applies to:
PeopleSoft Enterprise SCM eProcurement - Version 9.2 to 9.2 [Release 9]Information in this document applies to any platform.
Symptoms
Approve Change Request Not Showing Second Changes When Run Multiple Change Request
Multiple Change Request details not updating PO:
1. Issue 1. Looking at the change request details there is no information
2. Issue 2. On the second change request. On Review change request. There is no Change Request Details showing for the 2nd change request
3. Issue 3. Running the change req process again the PO does not update
The issue can be reproduced at will with the following steps:
Note: In the Replication Steps, User Details / Company Names / Addresses / Emails / Telephone Numbers / Etc. are fictitious (based upon made-up data used in the Oracle DEMO Environments), any similarity to actual persons, living or dead, is purely coincidental and not intended in any manner.
- Login as VP1 and Create epro requisition for Business Unit = ‘US003’. Submit. Navigation: eProcurement tile and then Create Requisition tile
- Login as Approver (VP2)
- Approve requisition. Navigation: Approval Tile
- Login again as VP1 and Budget Check Requisition. Navigation: My requisition tile. Go to Requisition Action
- Requisition approved and budget check valid
- Run Expedite Requisitions. Navigation: eProcurement > Buyer Center > Expedite Requisition
- PO Created. Approve PO and Dispatched. Navigation: Menu > Purchasing > Purchase Orders > Add/Update POs
- Go to My Requisitions tile
- Edit the Requisition to create a change request. Change quantity to 102
- Approve and budget check requisition
- Review Change Requests. Go to Change Request tile
- On detail is not showing any information. ==> Issue here
- Approve Change Requests. Navigation: Menu > Purchasing > Purchase Orders >Manage Change Orders > Approve Change Requests
- Run Process Change Orders. Navigation: Menu > Purchasing > Purchase Orders >Manage Change Orders > Process Change Orders
- Change order completed
- PO quantity updated
- Approve PO, budget check and dispatch. Navigation: Menu > Purchasing > Purchase Orders > Add/Update POs
- Now process a 2nd change request. Change quantity from 102 to 104. Navigation: Go to My Requisition tile. Edit Requisition
- Approve and budget check requisition
- Review change request. It is showing status completed and should show the new requisition changes. ==> Another issue here
- Change Request detail is not showing any information
- Go to Approve Change Request. It is already approved. Not showing the second changes. Navigation: Menu > Purchasing > Purchase Orders > Manage Change Orders > Approve Change Requests
- Due to the issue it is not possible to run change request
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |
References |