E-PRCS: Processes Remain In Pending Status In PSJob After Changing PSJob
(Doc ID 662460.1)
Last updated on DECEMBER 09, 2024
Applies to:
PeopleSoft Enterprise PT PeopleTools - Version 8.40 and laterInformation in this document applies to any platform.
SPECIFIC TO: PT8.4x, Process Scheduler
Symptoms
Two processes were added to an existing PSJob definition, which already had a queued instance.After the change the PSJob ran to success, however the last two processes are still in Pending status.
The PSJob had already been running as a recurrence when the definition changes were made.